The completion of thermal sliding test of Jinan new railway will end the history of freight train passing through the city
Public network · poster news Jinan December 12 (reporter Zhang Haizhen & nbsp; correspondent Du Buqing and Li Jinwen) on December 10, the thermal sliding test of the contact network project of the zh-2 standard of Handan Jinan Jiaoji contact line was successfully completed, and all test indexes met the requirements, laying a solid foundation for the joint commissioning and joint test of the whole line. The hot sliding test of the contact network project of the zh-2 section of the Hangji Jiaoji connecting line project undertaken by the China Railway 10th Bureau Group successfully completed the construction of the electric power company of the railway 10th Bureau of the
in more than eight months and successfully completed the construction tasks of each node. On November 19, the signal, electrification, power and communication engineering of Quanzhuang station was opened on time, the cold sliding of the contact network was successfully completed on December 4, the one-time power transmission of the contact network was successful on December 9, and the hot sliding test of the contact network was successfully completed on December 10, which provided a solid guarantee for the opening of the whole line. It is reported that the new Hanji Jiaoji connecting line project is a key project for the realization of the freight train outside the urban area of Beiyuan Daminghu pinglingcheng section in Shandong railway planning. After the opening of the project, all freight trains passing through Jinan Station will no longer cross the urban area of Jinan.