Completion of girder erection for Pingdu north station to Laixi North Station of Weilai high speed railway is expected to open to traffic by the end of 2020
Qilu.com · lightning news October 29 at 10:00 this morning, with the final box girder of Weifang Gaomi Dongwo Luozi super large bridge firmly seated, the beam erecting task of 647 hole box girder from Pingdu North Station of Weifang Laixi high speed railway to Laixi north station took 14 months to complete, officially entering the stage of online ballastless track construction, Weilai high speed railway is close to opening to traffic by the end of 2020. The
Weilai high speed railway project starts from Weifang North Station of Jinan Qingdao high speed railway, with a total length of 126 km. It passes through Changyi, Pingdu and Laixi of Weifang City, and connects to Laixi North Station of Qingrong intercity. There are four stations in the whole line, namely Weifang north station, Changyi south station, Pingdu north station and Laixi Northwest Station. The design speed is 350 km / h, and it is planned to be completed and opened to traffic by the end of 2020. The completion of the
Weilai high speed railway will relieve the pressure that the current ” schedule of Jiaoji passenger dedicated line has reached ”, provide objective conditions for the opening of more cross line bullet train lines for the Qingdao Rongcheng intercity line, put wings in the operation of the Qingrong intercity line, and activate the operation of the whole Qingrong intercity railway. At that time, the travel of citizens in Pingdu, Yantai, Weihai and other places will be more convenient. The time from Yantai and Weihai to Jinan will be shortened to two hours.