More than 85% of the infrastructure projects in front of the South Railway Station have been completed
Recently, the infrastructure construction scene in front of Panzhihua South Railway Station.
at present, the construction of infrastructure in front of South Railway Station has entered the stage of sprint and pre acceptance. 85% of the total amount of indoor decoration works of the hub in front of the station has been completed, 90% of the total amount of outdoor glass curtain wall, aluminum-plastic plate, glass roof installation, etc., 90% of the stone paving of the square in front of the hub gate, and 95% of the indoor landscape greening works. The special acceptance of pavement and slope structure has been completed for nazongbei section 2, nazongbei Road, Shagou road and zongle road of municipal road, the special acceptance of bridge has been completed for nazongbei bridge and nazongbei vehicular overpass, and the special acceptance of structure has been completed for flood discharge culvert of lines a, B and C. (Photo by song Junkang, reporter of Luo Zhongxin)